The New York Times
November 16, 2005
Transit Agency Authorizes Funds for 2nd Avenue Line
By SEWELL CHAN
After months of uncertainty about the pace and progress of the Second Avenue subway, a project that seems to be forever on the drawing board, the Metropolitan Transportation Authority intends today to authorize spending $150.4 million for the final design of a first segment, from East 96th to East 63rd Streets.
To be sure, the amount is but a fraction of the estimated $3.8 billion cost of the 2.2-mile segment, which is not projected to be completed until 2012 at the earliest. The entire 8.5-mile line would extend from 125th Street and Lexington Avenue in Harlem to Hanover Square in Lower Manhattan and cost $16.8 billion.
Still, the decision is the biggest financial affirmation of the authority's support for the project since November 2001, when its board awarded a $200.5 million contract to two engineering companies - Arup, a British company, and the DMJM Harris unit of Aecom - for preliminary engineering and design.
The move comes in the week after New York State voters approved a $2.9 billion transportation bond act that provided $450 million for the Second Avenue subway. The next step for the authority is to approach the Federal Transit Administration for an agreement that would secure support for the project. The authority wants the agency, part of the United States Department of Transportation, to pay about one-third of the total cost.
The article continues with a brief history of the 2nd Ave subway:
A subway line under Second Avenue has been an unfulfilled wish since 1929, when it was proposed as a replacement for the Second and Third Avenue elevated lines, which were later demolished. State voters have approved new debt to support the project before, in 1951 and 1967, and tunneling began in 1972. It was halted a few years later by the fiscal crisis.
The project's latest incarnation began in 2000, when the authority pledged $1.05 billion to revive the effort. Planners believe the new line would relieve congestion on the Nos. 4, 5 and 6 lines, which run under Lexington Avenue and are among the most crowded in the system.
To complete the first segment by 2012, the authority will have to move quickly. Officials said yesterday that they hope to award actual construction work by the end of next year - even though the final design could take until 2008 to complete. The biggest task is boring a two-track tunnel.
It should be noted that the site NYCsubway.org has a detailed page on the history of the 2nd Avenue Subway that goes into far greater detail.
Here's hoping this year's bond doesn't go the way of 1951 and 1967...
No comments:
Post a Comment